10 installations being decommissioned in the Sergipe-Alagoas Basin, Brazil, from 1 operator: status, type and expected completion year. ANP open data.
5
In progress
2
Planned
3
Completed
0
Suspended
Assets in this basin
- PLATAFORMA DE CAIOBA 1In progressFixed platform · CAIOBAN/D
- PLATAFORMA DE CAIOBA 2In progressFixed platform · CAIOBAN/D
- PLATAFORMA DE CAIOBA 3In progressFixed platform · CAIOBAN/D
- PLATAFORMA DE CAIOBA 4In progressFixed platform · CAIOBAN/D
- PLATAFORMA DE ROBALO 1In progressFixed platform · SALGON/D
- PCL-1 (Camorim)PlannedFixed platform · Camorim2031
- PBF-1 (Barra Sul, Furado)PlannedFixed platform · Furado2033
- PGU-1 (Guaricema)CompletedFixed platform · Guaricema2019
- PSGAL-1 (Dourado)CompletedFixed platform · Dourado2020
- Plataforma de Piranema (Piranema Spirit)CompletedFPSO · Piranema2025
What the asset dossier contains
One sheet per installation, with a public source (ANP and Ibama) and lookup date on every line. No estimate of mine mixed with what the agencies publish.
- Status of the decommissioning process on ANP’s panel (PDI and RDI), with the dates the panel shows.
- What the operator filed for the asset on ANP’s panel, out to 2059.
- Federal environmental licence of the installation, as published by Ibama.
- Decommissioning financial guarantee reported for the field.
- Operator of the asset, as published by ANP.
- Timeline: installation, expected start and completion of decommissioning.
Format: PDF sheet with a sources annex. Scope and timing agreed in the conversation.
Veridis Engenharia public catalogue built from ANP open data: name, basin, type, status, operator and years. The official source is the ANP website.