Subsea Decommissioning in Brazil: Pipelines, Wells & Manifolds
10 subsea assets (pipelines, wells and manifolds) under offshore decommissioning in Brazil, across 4 basins. ANP open data and per-asset technical dossier on request.
3
In progress
6
Planned
1
Completed
0
Suspended
Campos Basin (6)
- Poço ABL-1 (Albacora Leste)In progressWell · Albacora Leste2024
- Poço BCM-3 (Bicudo Cluster)In progressWell · Bicudo2025
- Duto GAR-CAB (Garoupa-Cabiúnas)PlannedSubsea pipeline · Garoupa2029
- Duto MRL-CAB (Marlim-Cabiúnas)PlannedSubsea pipeline · Marlim2031
- Duto SEAM (Espadarte-Albacora-Marlim)PlannedSubsea pipeline · Marlim2033
- Poço MLL-1 (Marlim Leste)CompletedWell · Marlim Leste2021
Santos Basin (2)
Espírito Santo Basin (1)
Potiguar Basin (1)
What the asset dossier contains
One sheet per installation, with a public source (ANP and Ibama) and lookup date on every line. No estimate of mine mixed with what the agencies publish.
- Status of the decommissioning process on ANP’s panel (PDI and RDI), with the dates the panel shows.
- What the operator filed for the asset on ANP’s panel, out to 2059.
- Federal environmental licence of the installation, as published by Ibama.
- Decommissioning financial guarantee reported for the field.
- Operator of the asset, as published by ANP.
- Timeline: installation, expected start and completion of decommissioning.
Format: PDF sheet with a sources annex. Scope and timing agreed in the conversation.
Veridis Engenharia public catalogue built from ANP open data: name, basin, type, status, operator and years. The official source is the ANP website.